12 workers can do a peice of work in 20 days. How many workers should be added to complete work in 16 days?​

Respuesta :

atchleyamirah69
atchleyamirah69 atchleyamirah69
  • 01-04-2021
3 workers

if 12 workers can do a piece of work in 20 days, then one person can do it in 240 days. 240/16 is 15. That is the number of workers that you need in total to it in 16 days. Since the question ask how many more workers,
15 - 12 = 3 more workers.
Answer Link

Otras preguntas

the benefits of struggling (speech)​
The table below shows the numbers of tickets sold at a carnival and the amounts of money in dollars collected Cost of Carnival Tickets Number of Tickets. Amount
The balance in Al's account is $ 32.60 . The balance in Dee's account is 3 4 the balance in Al's account. The balance in Zac's account is $ 49.08 less than the
You flip a coin 50 times. Of the 50 flips, the coin landed on heads 30 times. Use the questions below to compare the experimental probability of flipping heads
4. How many inches long is the hammer? 0_1 2 3 4 5 6
What was a nickname people used for early trains?
Identify and describe the main vegetation regions of Kenya and the world​
RT and UW are parallel lines Which angles are corresponding angles?
You have 4 pounds of peanuts. You want to put it in the bags so that there is 2/3 pounds in each bag. How many bags can you fill ?
what is the mineral salt intake of chlorophytes​