15men can complete a piece of work in25days. how many men should be added to complete the same work in15days.​

Respuesta :

mhanifa
mhanifa mhanifa
  • 04-08-2021

Answer:

  • 10 men

Step-by-step explanation:

Amount of work done by 15 men is:

  • 15 men *25 day = 15*25 man*days

Same work can be done by 25 men, in 15 days, so 10 more men should be added.

Answer Link
abovejosh
abovejosh abovejosh
  • 04-08-2021
Answer: 10 men explanation: guy above me
Answer Link

Otras preguntas

Write each pair of fractions as a pair of fractions with a common denominator 3/4 and 7/8
Which statistic best describes the favorite brand of jeans of 12-year old boys? A. mean B. median C. mode D. range
Who was known as the “king who lost America”? a. Henry VIII b. James II c. Edward VI d. George III
convert 12 kilograms to pounds
How do you turn 13/25 (fraction) into a decimal?
What is the purpose of a society's oral tradition? To emphasize the importance of sharing stories To entertain family members To give hope to the younger gen
Shelly made 5 more sales calls than Clark. Shelly and Clark made a total of 33 sales calls. How many sells did each of them make?
whats 600*50000+60 to this math problem
How do you factor 6x^2+14x+4
What kind of complement is the underlined word? September is the ninth month of the year. A. direct object B. predicate nominative C. indirect object